For years, the physical climate risk has appeared in reports as a contextual paragraph: «the site may be affected by episodes of heat or drought». No one disputed it because no one quantified it. That has changed. Today, a plant's exposure to extreme heat, water stress or torrential rain affects financing, insurance, permits and, above all, operational continuity.
The question is no longer whether to talk about climate change adaptation, but how to do it with a method that withstands an audit or a due diligence, and how to turn it into a defensible climate adaptation plan. What is physical climate risk and why is it urgent now
Physical climate risk is the possibility that climatic phenomena —acute, such as a heatwave or a flood, or chronic, such as the increase in average temperature or the reduction of water resources— damage assets, interrupt processes or increase operational costs. Unlike transition risk, which arises from regulatory or market changes, physical risk depends on
El risc climàtic físic és la possibilitat que fenòmens climàtics —aguts, com una onada de calor o una inundació, o crònic, com l'augment de temperatura mitjana o la reducció de recursos hídrics— danyin actius, interrompin processos o encareixin l'operació. A diferència del risc de transició, que prové de canvis normatius o de mercat, el risc físic depèn d' where the asset is and how it is designed.
Three changes have brought it from the context chapter to the decision-making table:
- European taxonomy. For an activity to be considered aligned and "not cause significant harm" to adaptation, a climate risk and vulnerability assessment proportional to the activity is required, as established in Appendix A of the Delegated Regulation (EU) 2021/2139.
- Sustainability information. Companies reporting under European standards (ESRS E1, Delegated Regulation (EU) 2023/2772, the annexes of which replace the Delegated Regulation (EU) 2026/1563 for financial years starting from 2027) must identify relevant physical and transition risks and explain how they manage them.
- Financiers and insurers. They request exposure data by location, not generic statements.
Four common errors in climate risk assessment
- Working at too large a scale. Assessing risk by country or region when the failure is a specific piece of equipment: a cooling tower, a well, a substation, or access.
- Looking only backwards. Using exclusively historical data in a climate that no longer behaves like the historical one.
- Not translating hazard into impact. Identifying heat or drought without converting them into downtime, water consumption, loss of performance, or cost.
- Ending up with a report, not a plan. Closing the study without prioritized, responsible measures or monitoring indicators.
How to conduct a defensible climate risk analysis in five steps
At auma we apply a method that connects climate science with asset engineering:
- Inventory of assets and critical dependencies. What must continue to function and what it depends on: water, energy, access, personnel and supply chain.
- Scenarios and horizons. Climate reference scenarios from the IPCC and horizons consistent with the asset's lifespan, typically 2030 and 2050.
- Exposure and vulnerability by hazard. Extreme heat, drought and water stress, flooding and heavy rain, wind and wildfire, analysed for each critical element.
- Operational and economic impact. Each hazard translates to days of downtime, cost overruns, production loss and regulatory risk, to allow comparison in the same unit.
- Adaptation and monitoring plan. Prioritised measures for cost-effectiveness, with responsible parties, timelines and indicators to be reviewed annually.
The result is a physical climate risk and vulnerability analysis that serves for taxonomy, for sustainability reporting and for investment decisions, and can be complemented with a climate change adaptation plan.
Adaptation is an engineering decision
Adapting is not adding an annex to the sustainability report. It is deciding where to install equipment, how to size a cooling system, how much water to guarantee or what redundancy a critical line needs. These are project decisions, with numbers, and the sooner they are incorporated into the design, the cheaper they are.
That is why we integrate it when decisions are already being made: an environmental permit, an expansion or the purchase of an asset. It is the approach of our solution for industrial climate resilience.
Frequently asked questions about climate risk and adaptation
Which companies need a climate risk assessment?
Those that want to align activities with the European taxonomy, those that report sustainability information and, in practice, any organisation with long-lived assets or with a high dependence on water and energy.
Is it the same as an environmental risk analysis?
No. The environmental risk analysis studies the damage that the activity can cause to the environment; the climate risk assessment studies how the climate can affect the activity. They are complementary.
How long does it take?
It depends on the number of sites and the information available. The inventory of critical assets already allows prioritisation of where to delve deeper.