auma prepared the complete documentation package for the authorisation of a ground-mounted solar PV plant in Penedès, for a renewable energy developer: the specific action project (PAE), the landscape impact and integration study (EIIP), theenvironmental impact assessment (EIA) and the bird study.
Project overview
| Client | Renewable energy developer (confidential) |
| Market | Renewable developers |
| Practice area | Energy transition |
| Location | Penedès (Spain) |
| Services | PAE · EIIP · EIA · Bird study |
| Year | 2025 |
The challenge
Ground-mounted PV plants in Catalonia require a set of documents examined simultaneously by planning, landscape and environmental bodies:
- Four documents, one project: PAE, EIIP, EIA and bird study must be fully consistent with each other.
- Sensitive territory: landscape and agricultural fit is the most scrutinised issue for sites in Penedès.
- Wildlife: birdlife is often the decisive environmental factor for a PV plant's feasibility.
The auma solution
auma drafts the four documents as a single technical package:
- One cartographic and project data basis for all documents, removing inconsistencies between files.
- Landscape and agri-environmental integration measures designed from project inception, not bolted on at the end.
- A bird study focused on identifying and mitigating the site's real risks.
The result
- Complete package delivered, ready for review by the renewable energy panels.
- One team and one technical basis for all the documentation.
- A methodology replicated across multiple PV plants throughout Catalonia.
In ground-mounted solar, the difference between a project that advances and one that stalls is almost always the quality and consistency of the initial documentation package.
Frequently asked questions
What documents are needed to permit a solar plant in Catalonia?
For plants on rural land: the specific action project (PAE), the landscape impact and integration study (EIIP), the environmental impact assessment where required under Law 21/2013 and Decree-Law 16/2019, and specific studies such as the bird survey.
What is a specific action project (PAE)?
The planning document that legitimises a public-interest facility on rural land, such as a PV plant: it defines the layout, access, services and the conditions for restoring the land at the end of the plant's life.
Is a bird study required for a PV plant?
At most sites, yes: the environmental body requires it to assess effects on steppe birds and raptors. Fieldwork properly scaled to the site can avoid information requests that delay permitting by months.
Developing a solar PV plant?
We draft the full package — PAE, EIIP, EIA and wildlife studies — on a single technical basis.
Let's talk about your project